MediumRoads

Adaptive Traffic Signal Project Bid Rejection

All four bids for the adaptive traffic control system were rejected — the low bidder pulled out and the rest came in over budget. The project will need to be rebid.

2 mentions (1 this month)Last discussed Oct 7, 2026
MediumRoads

Garfield Avenue speeding and safety

A resident reported repeated car crashes and speeding on Garfield Avenue and asked for warning signs, reflective striping, and buffer markings. Staff will follow up.

3 mentions (2 this month)Last discussed Oct 7, 2026
HighRoads

SGV Forward Bus Rapid Transit on Garvey and Atlantic

The council joined a four-city subcommittee (with Rosemead, El Monte, and South El Monte) to review and give feedback on the SGVCOG's proposed bus rapid transit lanes and signal upgrades along Garvey Avenue ahead of the 2028 Olympics.

4 mentionsLast discussed Sep 16, 2026
HighRoads

Transit services contract and zero-emission fleet

The city will pay Via $230,670 for a six-month pilot to shore up understaffed Dial-a-Ride service, and adopted its state-required zero-emission bus rollout plan.

5 mentionsLast discussed Aug 19, 2026
HighRoads

Potrero Grande Construction Traffic and Emergency Access

A resident described months of gridlock near the Costco center making it nearly impossible for her elderly mother and hospice-care uncle to get emergency help to their home. Council members asked staff to look at speeding up construction and possibly creating a business/resident impact fund.

2 mentionsLast discussed Aug 5, 2026
MediumRoads

Bus Line 70 Dedicated Bus Lane (SGV Forward)

Monterey Park is part of a joint effort with Rosemead, El Monte and South El Monte, coordinated through the San Gabriel Valley Council of Governments. This meeting was supposed to be a community briefing on it, but it fell apart when too few council members showed up.

2 mentionsLast discussed Jul 20, 2026
LowRoads

Pedestrian Safety at Riggin and Gerhart

A resident described aggressive drivers and wide streets at the Riggin/Gerhart four-way stop and asked the city to consider curb extensions and other redesigns, noting the fire department uses that route.

2 mentionsLast discussed Jul 15, 2026
MediumRoads

Link Shuttle Discontinuation

The Link, connecting Civic Center and Cal State LA, ends July 1 due to low ridership; riders can use Spirit Bus Route 5 along the same corridor.

3 mentionsLast discussed Jun 17, 2026
MediumRoads

Street Rehabilitation Contract Increase

Old water lines failed during repaving on Mira Valle, Grandridge Place, and Keller Avenue, forcing emergency repairs and a $445,665 contract increase with Onyx Paving. The project covers residential streets between Atlantic and Garfield.

2 mentionsLast discussed Jun 9, 2026
CriticalRoads

FY 2026-27 Capital Improvement Plan

The city has repaved 55% of its roads but faces an estimated $250-300 million in identified capital needs with only about $16 million slated for next year. Council members urged residents to attend budget workshops to help close the gap.

4 mentionsLast discussed Jun 3, 2026
MediumRoads

Courtyard Marriott Overflow Parking and Traffic

Residents near the Marriott complained that convention traffic (like Pokemon card events) clogs neighborhood parking from morning to night. The mayor said the big convention series has ended, and staff is talking with the hotel about parking fixes and possible permit parking options.

1 mentionLast discussed May 20, 2026
MediumRoads

Street sweeping services contract

After rejecting bids last year over cost spikes, the city locked in a five-year, roughly $1.1 million-a-year street sweeping deal with CMAX Commercial Services starting July 1.

1 mentionLast discussed Apr 15, 2026
LowRoads

GoSGV electric bike share program

Active SGV is offering Monterey Park residents year-long e-bike rentals for $75 and $2,000 vouchers toward cargo bike purchases, and asked the city to help spread the word.

4 mentionsLast discussed Apr 15, 2026
MediumRoads

Completed Capital Projects

Public Works wrapped up about 13 projects worth $9.5 million — including 10-plus miles of road resurfacing and the Emerson sewer line — mostly under budget, with 23 more in progress.

1 mentionLast discussed Mar 18, 2026